Botanic Highfields: Construction Update & Progress – March

Here’s what’s happening on-site:

* Entry Road Construction: Moving ahead rapidly! Drainage, kerbs, and road base are now complete. Asphalt is scheduled to be laid next week, and landscaping is well underway.

* Stage 1 & 2 Plan Sealing Update: Due to delays from the recent weather conditions, we anticipate lodging the plan sealing application in mid April.

Valuation Access: Valuations can proceed after plan sealing is achieved. Buyers will receive an email with access details.

* Registration: Timing will be subject to government authority timelines.

Stage 3 Progress: Advancing well! Road pavement is underway, kerb construction starts in late April, and retaining walls are progressing. Completion is targeted for late Q2.

Stay updated on milestones at https://botanichighfields.com.au/construction-update/